Scrum treats time as
one of the most important constraints in managing a project. To address the
constraint of time, Scrum introduces a concept called ‘Time-boxing’ which
proposes fixing a certain amount of time for each process and activity in a
Scrum project. This ensures that Scrum Team members do not take up too much or
too little work for a particular period of time and do not expend their time
and energy on work for which they have little clarity. Some of the advantages
of Time-boxing are as follows:
· Efficient development process
· Less overhead
· High velocity for teams
Time-boxing can be
utilized in many Scrum processes, for example, in the Conduct Daily Standup
process; the duration of the Daily Standup Meeting is Time-boxed. At times,
Time-boxing may be used to avoid excessive improvement of an item (i.e.,
gold-plating). Time-boxing is a critical practice in Scrum and should be
applied with care. Arbitrary Time-boxing can lead to de-motivation of the team
and may have the consequence of creating an apprehensive environment, so it
should be used appropriately.
The following meetings
are listed in the guide to the Scrum Body of Knowledge -
· Sprint—A Sprint is a Time-boxed iteration of one to six weeks
in duration during which the Scrum Master guides, facilitates, and shields the
Scrum Team from both internal and external impediments during the Create
Deliverables process. This aids in avoiding vision creep that could affect the
Sprint goal. During this time, the team works to convert the requirements in
the Prioritized Product Backlog into shippable product functionalities. To get
maximum benefits from a Scrum project, it is always recommended to keep the
Sprint Time-boxed to 4 weeks, unless there are projects with very stable
requirements, where Sprints can extend up to 6 weeks.
· Daily Standup Meeting—The Daily Standup Meeting is a short
daily meeting, Time-boxed to 15 minutes. The team members get together to
report the progress of the project by answering the following three questions:
1. What did I complete
yesterday?
2. What will I
complete today?
3. What impediments or
obstacles (if any) am I currently facing?
This meeting is
carried out by the team as part of the Conduct Daily Standup process.
· Sprint Planning Meeting—This meeting is conducted prior to the
Sprint as part of the Create Sprint Backlog process. It is Time-boxed to eight
hours for a one-month Sprint. The Sprint Planning Meeting is divided into two
parts:
1. Objective
Definition—During the first half of the meeting, the Product Owner explains the
highest priority User Stories or requirements in the Prioritized Product
Backlog to the Scrum Team. The Scrum Team in collaboration with the Product
Owner then defines the Sprint goal.
2. Task Estimation—During
the second half of the meeting, the Scrum Team decides “how” to complete the
selected Prioritized Product Backlog Items to fulfill the Sprint goal.
At times, the Task
Planning Meetings (conducted during the Create Tasks process) and the Task Estimation
Meetings (conducted during Estimate Tasks process) are also referred to as
Sprint Planning Meetings.
· Sprint Review Meeting—The Sprint Review Meeting is Time-boxed
to four hours for a one-month Sprint. During the Sprint Review Meeting that is
conducted in the Demonstrate and Validate Sprint process, the Scrum Team
presents the deliverables of the current Sprint to the Product Owner. The
Product Owner reviews the product (or product increment) against the agreed
Acceptance Criteria and either accepts or rejects the completed User Stories.
· Retrospect Sprint Meeting—The Retrospect Sprint Meeting is
Time-boxed to 4 hours for a one-month Sprint and conducted as part of the
Retrospect Sprint process. During this meeting, the Scrum Team gets together to
review and reflect on the previous Sprint in terms of the processes followed,
tools employed, collaboration and communication mechanisms, and other aspects
relevant to the project. The team discusses what went well during the previous
Sprint and what did not go well, the goal being to learn and make improvements
in the Sprints to follow. Some improvement opportunities or best practices from
this meeting could also be updated as part of the Scrum Guidance Body
documents.